Project Overview

This project involved the construction of a new air support unit building, comprising a helicopter hangar, offices and associated external works.

The building composition is reinforced concrete foundations, steel frame, composite cladding to roofs and walls with UPVC windows and doors. Wall finishes comprise mainly plaster and wall tiling and the floor finishes are carpet and vinyl sheeting with suspended ceilings throughout the offices.

External works comprised site clearance, concrete landing and service areas, paths, fencing, drainage and external services.

Project Gallery

Client

Dyfed Powys Police

Location

Pembrey

Project Value

£1.2m

Contract Period

26 weeks